I am pleased to report that the new Wastewater Plant is nearing the end of construction!
On Monday June 5th, we will be hauling in partially treated wastewater to properly "seed" the new plant and have it ready for treating our wastewater.
Overnight, from Midnight until 6:00am on June 6th, we will be completing the final tie-in of our sewer system into the new plant.
During this final connection, midnight to 6am, we are requesting residents of Nanton "refrain from the drain" to assist in this final connection.
For those 6 hours only, we would request you use as little water going down the drain as possible. Now, this isn’t a ban, so if you need to flush your toilet or take a shower or use water, PLEASE do so. We are only asking that residents avoid UNNECESSARY use of the wastewater system during these hours.
As of the morning of Tuesday June 6th, our new plant will be responsible for all of our wastewater treatment.
If you have any questions, please contact Kevin Miller, CAO at (403) 646-2029 or cao@nanton.ca.